C-Store & Gas Station
Explore: Real Projects, Real Solutions.
Dive into our Construction Case Studies page to explore firsthand accounts of real projects, showcasing our solutions and valuable insights for a comprehensive understanding of successful construction endeavors.
NEED ADVICE?
Submit Your Construction Worry & We'll Engineer You A Solution
Everything you need to turn your project into reality.
Submit An Inquiry
Sheetz
Challenge – the Developer needed to deliver a pad ready site at 98.5% compaction by December, but was in jeopardy with over $700,000 of additional site costs and winter conditions approaching after demolition of an existing industrial facility found 4-8 feet of unsuitable contaminated foundry sand under 80% of the slab.
Solution – As the Construction Manager, Fiorilli analyzed all options and navigated the best possible solution to mitigate remediation costs. In lieu of common alternatives such as export and fill, Fiorilli came up with a cement stabilization.
Results – The project was delivered on time and Fiorilli mitigated additional site costs saving the Developer from nearly $500,000 in unforeseen concealed site condition cost.